Extensions · Advice

Home extension advice from our architects: the checks to make before you design, the consents an extension can need, how to tender to builders and what to put in the contract.

Kitchen in a house extension with a glazed roof, an exposed brick wall and glazed doors to the garden
Franche Court Road, Earlsfield.

A successful home extension starts before the design. Get a measured survey and check the planning route, then find the drains, trees, boundaries and party walls that affect your site. Design with an architect, get Building Regulations approval, tender the full drawings to several builders, and sign a written building contract.

Key takeaways

  • Do the checks first: survey, planning history, drains, trees and neighbours. They shape what you can build and where.
  • Building within 3 metres of a public sewer usually needs a build-over agreement in Thames Water’s area.
  • Party wall notices go per neighbour. Our fee proposals suggest allowing about £1,000 for each one.
  • Tender a full drawing package to more than one builder and compare the quotes line by line before you sign a JCT contract.

The figures here are approximate and meant to give you an idea, not a quote. Every house and brief is different, so your costs and programme will depend on your project.

How to plan a successful home extension: 8 practical tips

These are the tips we’d give a friend about to extend. They follow the order the work happens in, from the first survey to the contract with your builder. Costs and timings have their own guides, which we link to as we go: the house extension cost guide covers prices per square metre, and our house extension timeline covers how long each stage takes.

1. Start with a measured survey and a desktop study

Everything else is drawn from the survey, so it comes first. A measured building survey gives your architect accurate plans, elevations, sections and levels of the house as it is. Before any design work, we also carry out a desktop study of the site’s constraints and the local planning rules for your house, such as whether it is listed or in a conservation area and whether earlier permissions carry conditions.

2. Settle the planning route early

Some extensions can be built under permitted development; others need a householder planning application. Our guide to planning permission vs permitted development explains the difference. Where the planning decision is the slow part, there are two ways to keep a project moving. On simpler schemes we can start the Building Regulations drawings while planning is pending, at the client’s risk, and we sometimes run a lawful development certificate for a permitted development scheme in parallel with a full application for a larger one.

3. Find the drains before you design

Drains often decide where an extension can go. In Thames Water’s area, building within 3 metres of a public sewer, or within 1 metre of a public lateral drain, usually needs a build-over agreement before work starts, and the charge depends on the pipe size. A CCTV drainage survey, with a camera run through the pipes, shows where the pipes run and what state they are in, which is why it sits on our list of surveys at the Building Regulations stage. Our page on the Thames Water build-over agreement explains the process.

4. Check the trees

Trees affect where foundations can go, and some need the council’s say-so before anyone touches them. A tree with a tree preservation order needs the council’s consent for works. In a conservation area, you must give the council six weeks’ notice before cutting down or pruning most trees: section 211 of the Town and Country Planning Act 1990 lets the work go ahead “after the expiry of the period of six weeks from the date of the notice” unless the council acts first. Check before you design, because a protected tree can rule out a layout.

5. Plan for the neighbours

Party wall notices go to each neighbour, and our fee proposals suggest allowing about £1,000 per neighbour; our party wall guide explains when you need them.

6. Treat Building Regulations as a design stage

Planning drawings show what the extension looks like. Building Regulations drawings show how it is built: the construction specification, foundation and drainage details coordinated with the structural engineer, thermal requirements and typical construction details. With a full plans application, building control must decide “within five weeks or, if you agree, a maximum of two months” (Planning Portal). Your builder prices from these drawings, and anything left open at this stage tends to come back as a variation on site.

7. Tender the full package and compare like for like

We send the design package to up to four vetted builders for tender. When the prices come back, we review each quote, put them side by side in a comparison spreadsheet, raise and answer the builders’ questions, and negotiate to an agreed contract value. A quote that looks cheap is often missing something, and the comparison is where that shows up. On one basement tender we reviewed in September 2026, the most common variation was a waterproofing system specified without the sump, pumps, alarm and discharge route it needs to work.

8. Sign a proper contract and check the insurance

Our usual building contract is the JCT Minor Works Building Contract with contractor’s design, now in its 2024 edition, with JCT Intermediate on larger jobs. It sets the price, the programme, how changes are valued and how payments are certified. We ask contractors for public liability cover of at least £5 million, the standard across our recent JCT contracts. Who insures the existing house and the new work differs from job to job, so read the contract and your own policy together; our house extension insurance guide goes through the options.

The consents and agreements an extension can need

Not every extension needs all of these, but rule each one in or out at the start. The table gives the current charges where they are set nationally or by the water company.

Consent or agreementWhen you need itChargeTime to allow
Householder planning permissionWhen the extension isn’t permitted development£548 from 1 April 2026; due to change around 8 December 2026 (proposed, subject to Parliament)We advise clients to allow about 3 months
Lawful development certificateTo confirm a scheme is permitted development£274Run alongside a planning application if useful
Building Regulations approvalAlmost every extensionSet by the building control bodyFull plans: 5 weeks, or up to 2 months by agreement
Party wall notices and awardsWork to a shared wall, on the boundary or near a neighbour’s foundationsAllow about £1,000 per neighbourAt least 2 months
Thames Water build-over agreementBuilding within 3m of a public sewer or 1m of a public lateral drain£130 (sewer 175mm or less), £490 (176 to 350mm), £585 plus legal costs from £1,000 (over 350mm)Before work over the pipe starts
Tree works notice or consentTrees in a conservation area, or with a tree preservation orderNo feeSix weeks’ notice in a conservation area
Consents and agreements for a house extension in London (fees as at October 2026)

The order things happen in

  • Survey and desktop study: the measured survey, and a check of the planning history and site constraints.
  • Concept and planning: sketch options, then the planning or permitted development drawings and application.
  • Technical design: Building Regulations drawings with the engineer, CCTV drainage survey, party wall notices and any build-over agreement.
  • Tender and contract: the package goes to builders, quotes are compared and the JCT contract is signed.
  • Build: building control inspections during the works, and the completion certificate at the end.

Our page on the home renovation process describes each stage, and what we do in it, in more detail.

Before you start

Plan your extension in ten steps

Our 10-step home design guide takes you through the stages of a project in order, from the first brief to the builder on site, so you know what to do next and who to ask.

Get the 10-step guide →

Worked example: third-party costs for a mid-terrace extension

Take a single-storey rear extension on a mid-terrace house in Thames Water’s area, with a 150mm public sewer running under the back garden and two neighbours who both need party wall notices. These are the charges that sit outside the build cost and your architect’s fees.

ItemBasisArithmeticAllowance
Householder planning applicationNational fee from 1 April 20261 × £548£548
Party wall, two neighboursAbout £1,000 per neighbour2 × £1,000£2,000
Build-over agreementThames Water Class 1, sewer 175mm or less1 × £130£130
Total£548 + £2,000 + £130 = £2,678£2,678
Worked example: third-party allowances for a mid-terrace rear extension (illustrative)

Building control charges and the fees for the engineer and surveys come on top, and are quoted for each job. Thames Water reviews its charges every April, and the £548 planning fee is due to change around 8 December 2026 under a proposed new national fee schedule, subject to Parliament, which would take it to about £575, so check both before you budget.

A custom house extension, designed for your house

Off-the-peg extension designs assume a standard house on a standard plot. A custom house extension starts instead from your survey and your brief. We draw up to three concepts in sketch form, using precedent images to test ideas, so you can weigh up layout and light against your budget before committing to one set of planning drawings.

Rear of a house with a timber-clad extension, large glazing and a steel stair down to the garden
Dagmar Road, Camberwell.

What to compare when the builders’ quotes come back

Quotes for the same drawings can differ a lot, so line up what is in each one before you look at the bottom line.

CheckWhy it matters
Is every item in the drawings and specification priced?Missing items come back later as variations, at a price you can’t compare
What is a provisional sum, and how big is it?Provisional sums are guesses for work not yet designed; large ones make a quote look cheaper than it is
What is excluded?Exclusions such as drainage, kitchens, flooring or decoration change the real cost
Programme and start dateA low price with a long programme can cost you more in rent or disruption
InsuranceAsk for the public liability certificate; we look for at least £5 million
What to compare between builders’ quotes for an extension

FAQs

What is a CCTV drainage survey?

A drainage contractor runs a small camera through the pipes from the manholes and records the route, size, depth and condition of each run. The report tells your architect and engineer where the pipes are before the foundations are designed, and whether any need repairing or diverting.

Can my architect start the Building Regulations drawings before planning is approved?

Yes, on simpler schemes. The risk is that the council asks for changes and some of the drawings have to be redone, so it suits projects where the planning outcome is fairly clear.

Do I need a structural engineer for a house extension?

Almost always. The engineer designs the foundations and the steels for any new openings into the existing house, and their foundation design is needed before party wall notices can be served.

Do I need an architect for a house extension?

No law says you must use one, but you will need drawings for planning and Building Regulations, and someone to coordinate the engineer and the surveys. An architect also runs the tender and can administer the contract, which is where much of the risk on a project sits.

Do I need permission to put in rooflights on an extension?

Rooflights usually go through as part of the permitted development or planning scheme for the extension. On a listed house or in a conservation area, check before you design them in, because they can change the roofscape the council is protecting.

Is a fixed price the same as a fixed final cost?

No. A fixed contract sum covers the work in the contract documents. Changes you ask for, and provisional sums firmed up on site, are added as variations, which is why a complete tender package matters.

More house extension advice on our blog

Our extension blog covers the choices that come up on London houses. If you’re weighing up the shape of the extension, read side return vs wraparound extensions.

Talk to an architect about your extension

Tell us about your house and what you need from the extension. In a consultation we’ll look at the planning route and the constraints on your site.

Sources

  • AURA Process Guide, February 2026: survey, desktop study, Building Regulations package and tender stage (AURA’s project files)
  • Thames Water, Do I need a build over agreement?: thameswater.co.uk, read 29 September 2026 (charges move every 1 April)
  • Town and Country Planning Act 1990, section 211: legislation.gov.uk
  • Planning Portal, Full plans: planningportal.co.uk, read 30 October 2026
  • Planning fees, annual indexation from 1 April 2026: assets.publishing.service.gov.uk
  • Planning Portal, Application fees England, from 1 April 2026 (works to protected trees: no current fee): planningportal.co.uk, read 2 November 2026
  • AURA’s fee proposals, JCT contracts (2021 to 2026) and a basement tender review (September 2026), AURA’s project files
Planning an extension?Book a consultation