Costs · Consultants and surveys

Which consultants and statutory fees a house extension or renovation needs, when each comes in, and what to budget for them from AURA’s figures and the official fee schedules.

Ground floor of a Brixton house opened through from the front room to the kitchen
Brailsford Road, Brixton.

How much do external consultants cost? On AURA’s projects, professional and statutory fees average about 12% on top of the builder’s price. Fixed items include £274 for a lawful development certificate and £130 to £585, plus legal costs on the largest class, for a Thames Water build-over agreement. AURA allows about £1,000 per neighbour for party wall costs, and engineers are priced per project.

Key takeaways

  • AURA’s cost guide puts professional and statutory fees at about 12% of the builder’s price, from its analysis of hundreds of projects.
  • Some charges are fixed and published: planning and lawful development certificate fees in the Planning Portal’s schedule, and build-over charges by Thames Water.
  • Party wall costs are per adjoining owner: AURA’s proposals allow about £1,000 per neighbour.
  • Engineer and building control fees are priced per project, so get quotes once the scope is known.

The figures here are approximate and meant to give you an idea, not a quote. Every house and brief is different, so your costs and programme will depend on your project. Statutory fees are those from 1 April 2026; Thames Water’s charges change every 1 April.

How much do external consultants cost?

Your builder’s quote and your architect’s fee aren’t the whole budget. A house extension or renovation can also need a structural engineer, surveys, party wall surveyors and statutory fees. AURA’s cost guide puts all professional and statutory fees together at about 12% on top of the builder’s price, and the table shows the items that make it up.

ItemWhen you need itBudget figure
Measured surveyBefore design startsPriced per house
Householder planning applicationIf the work needs planning permission£548; a rise to about £575 is proposed from around 8 December 2026, subject to Parliament
Lawful development certificateTo confirm permitted development in writing£274 (half the planning fee)
Planning Portal service chargeApplying online for an application with a fee over £100£149 including VAT for a householder application; £99 or £149 for an LDC
Structural engineerBeams, foundations and calculationsPriced per project; guide costs in AURA’s cost guide
Building controlEvery extension and structural alterationLocal authorities base fees on their costs; approvers agree fees with you
Party wall surveyorWork to a shared wall or near a neighbour’s foundationsAbout £1,000 per neighbour (AURA’s allowance)
Drainage CCTV surveyWhere the drain routes and depths aren’t knownPriced per survey
Thames Water build-over agreementIn Thames Water’s area, usually needed within 3 m of a public sewerClass 1 £130, Class 2 £490, Class 3 £585 plus legal costs from £1,000
External consultants, surveys and statutory fees on a house project, with the figures AURA uses (dated sources)

This page keeps to the consultants. For the full breakdown of a project budget, with AURA’s building rates and guide costs for engineers, see our house extension cost guide.

Your budget

Want a budget that includes everything?

We can look at your house and plans with you and set out which consultants and applications your project needs, and when each comes in.

Book a consultation →

Which consultants do you need for a house extension?

The design and the house decide which consultants you need: a party wall surveyor only where you build on or near a shared wall, a build-over agreement only near a public sewer, sound testing only where Part E asks for it. On AURA projects the team gathers quotes for these services on your behalf, though you can use another firm if you prefer.

StageConsultants and fees
Before designMeasured survey of the existing house
PlanningPlanning or lawful development certificate fee; other reports only if the council asks
Technical designStructural engineer; drainage survey where needed; building control application
Before the buildParty wall notices and awards; build-over agreement where needed
During and after the buildBuilding control inspections; sound testing where Part E applies
When each consultant comes in on a house extension (AURA process)

Our guide to acoustic testing explains when a sound test is needed. On projects with more than one contractor, CDM principal designer duties also come in; our guide to CDM duties on home projects explains who carries them.

How much does a structural engineer cost for an extension?

A structural engineer designs the beams that carry an opened-up wall, the foundations for an extension and the calculations that building control checks. The fee depends on how much structure changes: a single-storey rear extension needs less design than a side and rear extension with internal walls removed. AURA’s cost guide sets out guide costs by size of project, and the engineer quotes once the layout is agreed.

The engineer’s foundation design matters for more than building control. Party wall notices need it, so they can only be served once it exists.

Do you need a planning consultant as well as an architect?

On AURA projects the architect prepares the planning drawings, submits the application and acts as your agent through the planning process. The fixed costs are the statutory fees in the table above: £548 for a householder application or £274 for a lawful development certificate, plus the Planning Portal service charge if you apply online.

Our guide to how much an architect costs explains how design fees are worked out, and AURA’s own fees are on our fees page.

Party wall surveyor costs

Party wall costs are per adjoining owner, or per legal title, and each leaseholder needs their own notice. AURA’s proposals tell clients to allow about £1,000 per neighbour. It is an allowance, not a quote: surveyors price each job, and where a neighbour appoints their own surveyor instead of agreeing to one, the building owner pays that surveyor’s reasonable fee too, so the cost can rise above the allowance.

Notices need the engineer’s foundation design, so allow at least 2 months once it exists. Our party wall guide explains the notices and awards.

Thames Water build-over agreements and drainage surveys

In Thames Water’s area, building within 3 metres of a public sewer, or within 1 metre of a public lateral drain, usually needs a build-over agreement. The charge depends on the size of the sewer: Class 1 £130 for a sewer of 175 mm or less, Class 2 £490 for 176 to 350 mm, and Class 3 £585 plus legal costs from £1,000 for a sewer over 350 mm. The charges change every 1 April. Our page on the Thames Water build-over agreement explains the application.

Where nobody knows the drain routes, depths or condition, a drainage CCTV survey finds them before the foundations are designed.

Building control fees

Building control fees aren’t set nationally. Gov.uk says local authorities base their fees on their costs, taking into account the type of work, the site inspections and the floor area of an extension, while private registered building control approvers “negotiate their fees directly with you”. Our building control guide explains the two routes.

VAT on consultants’ fees

Check whether each quote includes VAT. AURA’s own fee proposals are quoted excluding VAT, and the Planning Portal’s service charge is quoted including VAT. Put every figure on the same basis before you add them up.

A CDM consultant

Where a project has more than one contractor, a principal designer has to be appointed under the CDM Regulations 2015. AURA’s 2024 job files hold proposals from a separate CDM consultant for that role on domestic projects, covering competency checks, pre-construction information, the HSE notification where needed and the health and safety file. The fee is quoted per project.

Worked example: the consultant budget for a rear extension

A single-storey rear extension to a mid-terrace house in Thames Water’s area, with a neighbour on each side, a Class 1 sewer within 3 m and a builder’s price of £120,000. The scenario is illustrative; the fees are those in force or used by AURA in November 2026.

ItemSumFigure
Householder planning applicationFee from 1 April 2026£548
Party wall, two neighbours (AURA’s allowance)2 × about £1,000about £2,000
Thames Water build-over, Class 1Charge from 1 April 2026£130
Fixed items above£548 + £2,000 + £130about £2,678
AURA’s 12% average for all professional and statutory fees£120,000 × 0.12£14,400
Worked example: statutory fees and allowances for one extension, against AURA’s 12% average (illustrative scenario)

The fixed items come to about £2,678 of AURA’s 12% average; design, engineering, surveys and building control are priced per project, and the £149 online service charge isn’t included. The cost guide linked above has the full breakdown.

Exterior architectural consultation: where to start

A consultation is the first step, before any consultant is appointed. AURA’s consultation is paid and starts with a desktop study of the property, followed by a meeting at your home or a video call, where the brief is tested against the house and the likely consultants are identified. After it, AURA sets out the design fee in writing.

Talk to us about your budget

Tell us about your house and what you want to build. In a consultation we’ll go through the consultants and statutory fees your project needs, so the budget covers them from the start.

FAQs

Do I need a planning consultant for a house extension?

On AURA projects the architect prepares and submits the planning application and acts as your agent through the planning process. The cost you can fix in advance is the statutory fee: the fee for a householder application is £548 today, with a change to about £575 proposed from around 8 December 2026, subject to Parliament.

How much does a structural engineer cost for a single storey extension?

The fee depends on how much structure changes. AURA’s house extension cost guide gives guide costs by size of project, and the engineer quotes once the layout is agreed.

How much should I budget for professional fees on an extension?

AURA’s cost guide puts professional and statutory fees at about 12% on top of the builder’s price, from its analysis of hundreds of projects. On a £120,000 build that is about £14,400.

How much does a party wall surveyor cost?

AURA’s proposals allow about £1,000 per neighbour. Costs are per adjoining owner, and if a neighbour appoints their own surveyor, the building owner normally pays that surveyor’s reasonable fee too.

How much is a Thames Water build-over agreement?

Class 1 £130 for a sewer of 175 mm or less, Class 2 £490 for 176 to 350 mm, and Class 3 £585 plus legal costs from £1,000 for a larger sewer. The charges change every 1 April.

How much are building control fees?

They aren’t set nationally. Local authorities base their fees on their costs, and registered building control approvers agree their fees with you, so get a quote for your project.

Does AURA arrange consultant quotes?

Yes. On AURA projects the team gathers quotes for consultants such as the structural engineer, party wall surveyor and drainage survey on your behalf, though you can use another firm if you prefer.

Sources

  • Planning Portal, application fees in England from 1 April 2026: planningportal.co.uk
  • Planning Portal, How much does a planning application cost? (service charge bands): planningportal.co.uk, read 10 November 2026
  • Thames Water, Do I need a build over agreement?: thameswater.co.uk
  • GOV.UK, Building regulations approval: How to apply (fees and costs): gov.uk, read 10 November 2026
  • AURA house extension cost guide, AURA Process Guide v5 (August 2026) and AURA fee proposals
Budgeting for your project?Book a consultation