Planning · Timelines
How long a planning application takes in England, stage by stage: the legal decision periods, what slows a council down, how your own council performs, and what to do if it runs late.

For a householder application, such as an extension, the council has 8 weeks to decide, counted from the day after it receives a valid application. Major schemes have 13 weeks, or 16 with an environmental impact assessment. Allow time before that to prepare the application. In April to June 2026, 92% of householder applications in England were decided within 8 weeks or an agreed longer time.
Key takeaways
- The council has 8 weeks for a householder or other non-major application, 13 weeks for a major one, and 16 where an environmental impact assessment is needed.
- Neighbours are told with a site notice displayed for at least 21 days, or a letter to adjoining owners or occupiers.
- Councils can agree a longer period with you in writing. In the two years to June 2026, about 4 in 10 non-major decisions in England were made under an agreed extension of time or similar agreement.
- If a non-major application is still undecided after 16 weeks, with no extension agreed and no appeal made, the fee is refunded.
- Once you have permission, you have 3 years to start work.
- In our proposals we allow about 2 weeks for validation and 8 weeks for a decision. We tell clients to allow about 3 months in all, because councils often run late.
The figures here are approximate and meant to give you an idea, not a quote. Every house and brief is different, so your costs and programme will depend on your project.
Contents
How long does planning permission take?
Once the council has a valid application, it has 8 weeks to decide a householder or other non-major application and 13 weeks for major development. Where an environmental impact assessment is required, the limit is 16 weeks. The clock starts the day after the council receives the valid application, so the time you spend preparing it comes first.
These are the statutory periods for England, set by the Development Management Procedure Order 2015 and the government’s planning guidance. They apply to every council, from Wandsworth to the smallest district council. What differs from one council to another is how often it meets them, which we come to below.
| Application | Time the council has to decide | Counted from | Source |
|---|---|---|---|
| Householder application (an extension, or a dormer that needs permission) | 8 weeks | The day after a valid application is received | DMPO 2015 art. 34; GOV.UK guidance (8 Apr 2026) |
| Full application for other non-major development, such as a small change of use | 8 weeks | Same | Same |
| Major development (for example 10 or more homes) | 13 weeks | Same | Same |
| Development needing an environmental impact assessment | 16 weeks | Same | GOV.UK guidance (8 Apr 2026) |
| Any of the above, by agreement | A longer period agreed in writing | As agreed | DMPO 2015 art. 34; GOV.UK guidance |
You’ll see these periods called the determination period. The council’s letter acknowledging a valid application gives a target date, which is the end of that period. It’s the date the council works to.
The planning permission timeline, stage by stage
A planning application runs in five stages: optional pre-application advice, preparing and submitting the application, validation, publicity and assessment, and the decision. Only the decision has a legal time limit. The stages before it depend on how complete the application is and how busy the council is, so they’re where most of the variation comes from.
| Stage | What happens | How long | What sets the length |
|---|---|---|---|
| Pre-application advice (optional) | The council’s planning team gives written advice on your proposal before you apply | No statutory period; each council sets its own service and fee | The council’s own service standard |
| Preparing the application | Survey, design, drawings, forms, any supporting reports and the fee | Depends on the brief and the reports the council needs | How settled the brief is, and which reports the council needs |
| Validation | The council checks the forms, drawings, documents and fee before the clock starts | No statutory period | Whether anything is missing or wrong |
| Publicity and consultation | A site notice or letters to neighbours; consultees such as highways or conservation may comment | Site notice displayed for at least 21 days | Fixed minimums, inside the 8 weeks |
| Assessment | The officer visits, weighs the scheme against local policy and may ask for changes | Inside the 8 weeks | Objections, amendments, the officer’s workload |
| Decision | Made by a planning officer or, for some applications, the planning committee | By the end of week 8, or the date you agree | The council’s rules on who decides what |
| After the decision | Discharging conditions, building regulations, party wall notices, tender | Permission lasts 3 years to start work | Your programme |
The 8-week clock for a householder application
- Day 0: the council receives a valid application, with the right forms, drawings and fee.
- Day 1: the 8 weeks begin.
- Early in the period: neighbours are told by site notice (up for at least 21 days) or letter, and consultees are asked.
- Through the period: the officer visits, assesses the scheme and may ask for amendments.
- End of week 8: the decision is due, unless you’ve agreed a longer period in writing.
- Week 16: if there’s still no decision, no agreed extension and no appeal, the fee is refunded.
Only day 1, the end of week 8 and week 16 are fixed by the rules. The order in between varies from council to council.
Pre-application advice
Before you apply, you can ask the council for written advice on your plans. It isn’t required, and there’s no legal time limit for the reply: each council publishes its own service, fees and response times on its website. It’s most useful when a scheme is close to a policy line, such as a large extension in a conservation area.
Submission and validation
You can apply online through the Planning Portal or directly to the council. The council then checks that the forms, drawings, documents and fee are all there and correct. Only then is the application valid and the 8 weeks running. Each council publishes a local validation checklist, and an application that misses an item is held until it’s fixed. In our proposals we allow about 2 weeks for validation.
Publicity and consultation
For a householder application, the council either displays a site notice on or near the property for at least 21 days, or writes to the adjoining owners or occupiers. It also puts the application on its website, and the deadline for comments can’t be less than 14 days after that. Neighbours, local councillors and consultees such as the conservation officer can comment. All of this happens inside the 8 weeks.
Assessment and decision
The case officer visits the site, reads the comments and weighs the scheme against the local plan. If something small stands in the way, the officer may ask for amended drawings rather than refuse. Each council’s own rules say which applications its officers can decide and which go to the planning committee, which meets on fixed dates.
How long does planning permission take for an extension?
An extension to a house is a householder application, so the council has 8 weeks from the day after it receives a valid application. That period is the same for every council in England. Add the time to design and draw the scheme before you submit, and the time after approval for building regulations and tender.
Some extensions don’t need a planning application at all: our planning permission vs permitted development guide explains when.
Planning is one part of the programme. If you want the whole run from first drawing to moving back in, our guide to how long a house extension takes in London covers design, approvals, tender and build.
Why is your planning application taking so long, and can you speed it up?
Most delays come from a handful of causes: an application that isn’t valid, a request for more information, objections that send it to committee, a conservation area or listed building, or a council with more applications than officers. You can head off most of them before you submit. The table shows what each one does to the clock.
| Cause | What it does to the clock | What helps |
|---|---|---|
| Incomplete or invalid application | The 8 weeks don’t start until it’s valid | Check the council’s validation checklist; submit complete drawings and the right fee |
| Request for more information | Can push the decision past week 8, often with an agreed extension | Include the reports the council’s checklist asks for; reply within days |
| Amendments during assessment | Small changes may fit in the 8 weeks; bigger ones may need re-consultation | Design to the council’s guidance from the start; talk to the officer early |
| Objections and committee | Committees meet on set dates, which can move the decision | Show neighbours the plans before you apply; design out overlooking and overbearing walls |
| Conservation area or listed building | Extra consultation (conservation officer); listed building consent runs alongside | A heritage statement and drawings that show the historic fabric clearly |
| Council workload | Delays unrelated to your scheme | Check your council’s record (below); allow for it in your programme |
The council’s process sets the pace. What you can control is how often the clock stops. Start with a valid, complete application. After that, reply to the officer quickly, follow the council’s design guidance, and show the neighbours the plans before you apply.
Does it depend on your council?
The legal period is the same everywhere, but how councils meet it varies. Government figures for the two years to June 2026 show that across England, about 54% of non-major decisions came within 8 weeks and about 40% were made under an agreed extension of time or similar agreement. Overall, 91% were made within 8 weeks or the agreed time.
| Council | Non-major decisions (2 years) | Decided within 8 weeks | Decided under an agreed extension | On time (8 weeks or agreed date) |
|---|---|---|---|---|
| England | 502,948 | 54% | 40% | 91% |
| Wandsworth | 3,781 | 55% | 37% | 91% |
| Lambeth | 2,731 | 50% | 47% | 94% |
| Merton | 2,121 | 49% | 41% | 88% |
| Richmond upon Thames | 3,583 | 65% | 31% | 95% |
| Hammersmith and Fulham | 2,309 | 32% | 65% | 87% |
| Kensington and Chelsea | 3,228 | 47% | 51% | 94% |
| Southwark | 2,260 | 64% | 34% | 94% |
| Kingston upon Thames | 2,076 | 73% | 19% | 89% |
| Bromley | 4,156 | 61% | 30% | 86% |
Official figures from MHCLG live table P153 (July 2024 to June 2026, provisional, published 24 September 2026). The columns are separate measures and are not additive: “within 8 weeks” and “under an agreed extension” don’t add up to “on time”. Non-major decisions include householder applications, minor developments and changes of use. “Agreed extension” also counts planning performance agreements and environmental impact assessment cases. Rounded to the nearest whole per cent.
To check any council in England, look it up in the government’s live table P153, which is updated every quarter. For your own application, the council’s online planning register shows the target date and every document as it comes in.
What if the council doesn’t decide in time?
If the council needs more time, government guidance says it should ask you to agree a longer period, in writing, with a date for the decision. If you don’t agree and the period passes, you can appeal to the Planning Inspectorate for non-determination. If a non-major application is still undecided after 16 weeks, with no extension agreed and no appeal, the fee is refunded.
The rule: the government’s planning guarantee says a non-major application should be decided within 16 weeks (26 for major), and no application should spend more than a year with decision-makers, including any appeal. If the council misses 16 weeks without an agreed extension, and you haven’t appealed, it refunds the planning fee. A householder application in England currently costs £548 (fee schedule from 1 April 2026).
Agreeing an extension makes sense when the officer is close to a positive recommendation and needs a small change. Appealing for non-determination takes the decision away from the council altogether, and householder appeals take time too: for appeals decided in June 2026, the median was 12 weeks.
If the application is refused, the decision notice gives the reasons. You have 12 weeks from the date on the decision letter to appeal a householder refusal, or you can revise the scheme and apply again. Our guide to why planning permission is refused, and what to do next covers both routes.
A worked example: an extension application from submission to decision
Take a rear extension in a London borough, with a complete application that the council receives on Monday 2 March 2026. The 8 weeks begin the next day, so the decision is due by Monday 27 April. If the council needs more time and you agree, the new date goes in writing. If nothing is agreed and there’s no decision by Monday 22 June, the fee is refunded.
In practice, we’d allow about 2 weeks before 2 March for validation, and tell the client to plan on about 3 months from submission to decision, because councils often run late.
| Date | What happens | Why that date |
|---|---|---|
| Before submission | Survey, design and planning drawings | Length depends on the brief |
| Mon 2 March 2026 | The council receives a valid application | Complete forms, drawings and fee |
| Tue 3 March | The 8-week period starts | The day after receipt |
| March | Site notice up for at least 21 days, or letters to neighbours | Minimum publicity |
| Mon 27 April | Decision due | End of the 8 weeks |
| Mon 22 June | Fee refunded if still undecided, with no extension agreed and no appeal | End of week 16 |
| Within 3 years of the decision date | Work must start | How long permission lasts |
Once the decision is in, conditions, building regulations and party wall notices come next. Our guide to what happens after planning approval takes it from there.

First step
Test the planning route on your own house
Our Concept Feasibility Package sets out sketch options for your house and a preliminary cost plan, so you know what’s likely to need permission before you commit to full drawings.
What we’d do to keep a planning application on time
Most of the time you can save is won before the application goes in. Before quoting, we run a desktop study of the house and research the borough’s planning policies, so the design starts from what the council is likely to accept. From there, these habits keep the 8 weeks running.
Submit it complete. Check the council’s local validation list and send everything it asks for, including any heritage or tree reports, so the clock starts the first time.
Design to the council’s guidance. Most boroughs publish design guidance for extensions and roofs. A scheme that follows it gives the officer fewer reasons to ask for changes.
Talk to the neighbours first. A neighbour who has seen the drawings is less likely to object, and fewer objections mean less chance of committee.
Answer the officer quickly. When an officer asks for a small amendment late in the period, a reply within days can be the difference between a decision on time and an extension.
Start the building regulations drawings while planning is pending. On simple schemes, we can start them during the 8 weeks, at the client’s risk: if the council asks for changes, some drawings may need redoing, but the time after approval is shorter.
Run a lawful development certificate and a full application in parallel, where it fits. When part of a scheme may be permitted development, applying for a certificate alongside a full application for the larger scheme gives you a fallback if the full application is delayed or refused.

FAQs
How long does retrospective planning permission take?
A retrospective application is a planning application, so the same periods apply: 8 weeks for a householder application, from the day after the council receives a valid application. What’s different is the risk. If it’s refused, the council can take enforcement action, so the work may have to change or come out. Our guide to building without the right consent explains what happens.
How long does planning permission last?
Three years from the date it’s granted, unless the decision notice sets a different period. Work has to begin within that time, not finish. Any conditions that must be met before work starts have to be discharged first, which our guide to what happens after planning approval covers.
Can I start work before the decision?
Not on anything that needs the permission. If you build it and the application is refused, the council can take enforcement action. Work that doesn’t need planning permission isn’t affected. If you’re unsure whether something needs permission, a lawful development certificate settles it, with an 8-week statutory period.
Does a planning committee add time?
It can. Each council’s own rules set which applications its planning officers decide and which go to the planning committee, for example where there are objections or a councillor asks for it. Committees meet on set dates, so a committee case may need an agreed extension.
How long does a planning appeal take?
In June 2026, householder appeals decided on written evidence took a median of 12 weeks, and 14 weeks on average, according to the Planning Inspectorate. You have 12 weeks from the date on the refusal letter to appeal a householder decision.
Talk to an architect about your house
Tell us what you’d like to build. We’ll tell you which planning route it needs and what your council is likely to ask for, in a consultation. Our planning service takes it from there.
Sources
- GOV.UK, Determining a planning application (planning practice guidance, paragraphs 001 to 004, updated 8 April 2026): https://www.gov.uk/guidance/determining-a-planning-application
- The Town and Country Planning (Development Management Procedure) (England) Order 2015, articles 15 and 34: https://www.legislation.gov.uk/uksi/2015/595/article/15 and https://www.legislation.gov.uk/uksi/2015/595/article/34
- Town and Country Planning Act 1990, section 91: https://www.legislation.gov.uk/ukpga/1990/8/section/91
- MHCLG, Live tables on planning application statistics, Table P153 (July 2024 to June 2026, provisional; page updated 24 September 2026): https://www.gov.uk/government/statistical-data-sets/live-tables-on-planning-application-statistics
- MHCLG, Planning applications in England: April to June 2026 (released 24 September 2026): https://www.gov.uk/government/statistics/planning-applications-in-england-april-to-june-2026/planning-applications-in-england-april-to-june-2026-statistical-release
- GOV.UK, Appeals: how long they take (June 2026 figures, updated 30 July 2026): https://www.gov.uk/guidance/appeals-how-long-they-take
- GOV.UK, Appeal a householder planning decision: https://www.gov.uk/appeal-householder-planning-decision/how-long-you-have-to-appeal
- MHCLG, Fees for planning applications in England from 1 April 2026 (householder application £548): assets.publishing.service.gov.uk; Planning Portal, English planning application fees increase on 1st April 2026 (30 January 2026): blog.planningportal.co.uk
- AURA fee proposals: allowances for validation and decision
Contents