|| The home renovation process

Every home renovation goes through the same ten steps.

Here they are in order, from the first call to moving back in, shown on Norman Park, an award-winning family home in Bromley. Your own project will follow the same steps, at its own pace.

or see all ten
The same view before: a white-rendered house with small windows and a tiled roof
The back of the house after: a copper-clad gable with a wide window, and full-width glazing to the garden
AfterBefore
Drag to compareSlide to compare
01 Before10 After

|| Optional

Your project. Your dates.

See roughly when each stage of your home renovation could happen.

|| The renovation process, mapped

Ten stops. Tap one to look inside.

    || In writing

    The home renovation process, step by step.

    The same ten steps in words, for anyone who prefers to read. Building an extension in particular? There is also a fuller guide to building an extension.

    01

    Getting started

    A short call, then a consultation at home or by video.

    It starts with a conversation about what you have in mind. A few photos of the house and a rough idea are plenty. Then comes a meeting at the house, or a video call if that’s easier.

    You decide
    A visit to the house, or a video call
    How long
    One call, then one meeting
    Your architect
    Listens first, then says honestly what looks possible

    At Norman Park: A Tudor-style family house in Bromley, with dated rooms, small windows and an old garage at the back. The family wanted space and light, and to stay put.

    02

    Survey and first look

    The house is studied and measured, then a written fee proposal follows.

    The architect checks the planning history of the street and the council’s rules. A measured survey then records the house exactly as it is, so every drawing starts from real dimensions.

    You decide
    Your brief: what you need, your budget and the feel you like
    How long
    About 3 to 4 weeks
    Your architect
    Turns the survey into accurate drawings of the house today

    At Norman Park: April 2023: every room, wall and roof measured. The drawings showed a house with good bones and a back that turned away from a long garden.

    03

    Design options

    A few ideas for the space, sketched and then in 3D.

    Different ways the house could work are sketched first. The strongest are then shown as plans and 3D views, so you can see the space before choosing.

    You decide
    Your favourite option, and what to change
    How long
    About 4 weeks
    Your architect
    Draws the options and talks you through each one

    At Norman Park: May to June 2023: a first concept, then four ways to shape the back of the house. The family chose a pitched gable with a wide window under it.

    04

    Planning permission

    The application is prepared and sent for you. Some projects don’t need it at all.

    The architect prepares the drawings and sends them to the council. They check the application first, then usually decide within 8 to 12 weeks. Many lofts and rear extensions are “permitted development” and need no application.

    Building regulations and detailed design can start while the council decides, so no weeks are lost.

    You decide
    Sign off the drawings before they go in
    How long
    About 8 to 12 weeks, if it’s needed
    Your architect
    Deals with the council for you, start to finish

    At Norman Park: Sent to Bromley Council on 31 July 2023 and approved on 26 September, in under nine weeks. A smaller second application, for glazing in the front gable, was approved that December.

    05

    Building regulations

    A separate approval that the build is safe, warm and sound.

    Technical drawings and the structural engineer’s calculations go to Building Control, and an inspector visits during the build. Neighbours who share a wall also need formal notice under the Party Wall Act.

    You decide
    Very little. Each form is explained as it comes up
    How long
    Runs alongside planning
    Your architect
    Coordinates the engineer, Building Control and the neighbours’ notices

    At Norman Park: The building regulations package was submitted in February 2024 and approved in March.

    06

    Detailed design

    Every finish decided on paper, so nothing is left to guesswork.

    Floors, walls, joinery, lighting, heating and sockets are set out in a written specification, so every builder prices exactly the same house.

    You decide
    Finishes, lighting and the details that make it yours
    How long
    Alongside planning
    Your architect
    Writes the specification and draws the details

    At Norman Park: A full specification went to the builders in February 2024, so every price covered the same house, down to the roof junctions.

    07

    Interior design

    Optional: the look and feel, chosen together.

    Mood boards, materials, colours and fittings, with the kitchen planned alongside. Everything can be sourced and ordered for you.

    You decide
    The look you love
    How long
    At your pace
    Your architect
    Uses trade accounts that typically save clients 5 to 15%

    At Norman Park: Finishes were chosen with the family from October 2023: dark joinery, pale oak and warm stone, carried through the kitchen, the stair and the bathrooms.

    08

    Choosing a builder

    Three or four builders price the same drawings.

    Each builder prices the full set of drawings and the specification, so you compare like with like. The prices are then compared with you, and the building contract is set up.

    You decide
    Which builder you choose
    How long
    About 4 to 6 weeks
    Your architect
    Runs the process and explains the differences between the prices

    At Norman Park: Builders priced the full set of drawings in March 2024. The chosen builder started on site at the end of April.

    09

    On site

    Building starts, with optional site visits twice a month.

    Site visits are optional. With them, the architect checks progress, answers the builder’s questions, meets Building Control and sends you a short photo report after each visit.

    You decide
    Small choices as it comes together
    How long
    About 4 to 6 months for a single-storey extension
    Your architect
    Optional visits twice a month to keep the build on track

    At Norman Park: Building ran from spring 2024. The new roof and the gable went up that autumn, with site visits and photo reports along the way.

    10

    Enjoy your new home

    Move back in and enjoy the space you planned.

    Final inspections and sign-off, then it’s yours to enjoy.

    You decide
    Any final touches before sign-off
    How long
    Final inspections, then it’s yours
    Your architect
    Still a call away if you need anything

    At Norman Park: A two-storey rear, a loft with a wide gable window and an open ground floor that runs into the garden. The family moved home in autumn 2025, and in 2026 it was named a winner at the UK Property Awards.

    || Your turn

    Ready to start yours?

    Talk your project through with an architect, or see what a renovation costs per square metre in London.

    Timings are typical for London. Your architect will give you a programme for your own house.